PROJECT of THE First Affiliated Hospital of Zhengzhou Emergency center Doorway/SignMaking

2024-09-21

Latest Company Case About PROJECT of THE First Affiliated Hospital of  Zhengzhou Emergency center Doorway/SignMaking

Project name:Maintain Emergency Center Doorway Ceiling

Project location: THE FIRST AFFILIATED HOSPITAL OF ZHENGZHOU UNIVERSITY Emergency CENTER Doorway Ceiling

Project commencement date:08/01/24

Estimated completion date: 30/01/24

latest company case about PROJECT of THE First Affiliated Hospital of  Zhengzhou Emergency center Doorway/SignMaking  0

I. Project Overview

The purpose of this project is to maintain Doorway Ceiling with a total gross floor area of [2600m²] square meters.The core advantage of using aluminum veneer for hospital exterior walls lies in its ability to present a unified and clean appearance, along with being easy to install and maintain. Aluminum veneer can create a seamless and consistent visual effect on the hospital exterior, giving it a professional and tidy look that is essential for a healthcare facility. Its installation process is relatively straightforward, which not only saves time and labor during construction but also reduces the complexity and potential difficulties. Moreover, the ease of maintenance is a crucial factor. It allows for simple and efficient upkeep, ensuring that the exterior walls can always maintain their good condition with minimal effort. This means that any dirt, stains, or minor damages can be quickly addressed, keeping the hospital's exterior looking fresh and well-maintained over time. Overall, these characteristics make aluminum veneer an ideal choice for hospital exteriors, meeting the practical and aesthetic needs of the healthcare environment.

 

 

The project overall it was quick that started with a deposit, the production of the keel, the steel frame behind the panels, took a week, the panels took 8 days to produce, and the labor installation took a week.

latest company case about PROJECT of THE First Affiliated Hospital of  Zhengzhou Emergency center Doorway/SignMaking  1

II. Progress of the Project

 

-Now, the foundation works have been completed by 100%, and the main structure construction has reached final stage

- Decoration works are about to start and relevant materials are ready.

2. Quality control

- The construction is carried out in strict accordance with the construction specifications and quality standards, and quality inspections are carried out regularly.

- The completed part of the project has been inspected and the quality meets the requirements, and no major quality problems have been found.

latest company case about PROJECT of THE First Affiliated Hospital of  Zhengzhou Emergency center Doorway/SignMaking  2

3. Safety management

- The construction site has been set up with perfect safety protection facilities, and regular safety training has been provided to workers.

- Up to now, no major safety accidents have occurred.

latest company case about PROJECT of THE First Affiliated Hospital of  Zhengzhou Emergency center Doorway/SignMaking  3

III. Problems encountered and solutions

1. Problems

- The construction process encountered typhoon,rain and wind which could be affected the progress of the project.

- Some Communication is in conflict ,Financial situation of customers that payment were not supplied in time, resulting in a short stoppage of construction.

2. Solution

- In response to the weather problems, Reinforcement of support, adjusting construction time,were taken.

- Enhanced communication and coordination with customers to ensure timely supply of materials.

 

IV. Next Plan

1. Accelerate the progress of the project to ensure that the main structure is completed on time.

2. strengthen the quality supervision, and focus on the key parts of the control.

3. do a good job in the preparation of decorative works to ensure smooth convergence.

latest company case about PROJECT of THE First Affiliated Hospital of  Zhengzhou Emergency center Doorway/SignMaking  4

V. Summary

Although some problems have been encountered, they have been solved through effective measures. In the subsequent construction, we will continue to strengthen management to ensure that the project is completed on time and with high quality.

 

latest company case about PROJECT of THE First Affiliated Hospital of  Zhengzhou Emergency center Doorway/SignMaking  5

Advantages:

 

High Durability

Aluminum veneer shows great durability. It can resist natural factors like sun, rain, and temperature changes. In any environment, it stays in good condition, unlike wood that rots or plastic that fades. Its stability and resistance make it reliable for long outdoor use.

Appropriate Material Strength

It has enough strength for external impacts. Daily collisions won't damage it easily. Its metal nature ensures integrity, useful in various installations and against wear and tear. It's a strong yet practical choice for house numbers.

II. Aesthetics

Diverse Surface Treatments:

With various treatments like anodic oxidation and fluorocarbon spraying, it gets different looks. It can be shiny or in any color, matching building styles. This customization adds elegance and style to the entrance or facade.

Flexible in Shaping Design

Its plasticity allows unique shapes. From simple to creative, it suits different styles. On modern buildings, it stands out, adding individuality. It can be shaped to fit any design vision, making the property more memorable.

III. Convenient Installation and Maintenance

Simple and Quick Installation

Installing is easy with screws, glue, or accessories. No complex tools or skills needed. Its light weight helps. Easily replaceable or adjustable, it's practical for new builds and renovations.

Easy to Clean and Maintain

Cleaning is simple with a damp cloth. Minor scratches can be fixed easily. Low-maintenance, it always looks good, saving time and effort. Popular with property owners for its convenience.